Launch plan: endusers.cncf.io — KubeCon NA 2026

This document is the date-backed launch plan called for by issues #90 (no launch/promotion strategy), #100 (no success metrics), and #104 (KubeCon NA 2026 launch window). It converts those findings into a single countdown.

Launch event: KubeCon + CloudNativeCon North America 2026, November 9–12, Salt Lake City. This plan was drafted on 2026-08-08, 13 weeks out from the launch Monday of 2026-11-09. See the timeline table below for the current week-by-week status — it uses explicit dates and does not go stale.

Goals

  1. Announce the site to the CNCF End User Community during KubeCon week with every content pillar (architectures, metrics, awards, community, events, blog) current as of launch day.
  2. Convert launch attention into durable contribution: good-first-issues labeled, CONTRIBUTING path verified by a non-author, maintainer bus factor > 1.
  3. The ownership question (ADR 0001, issue #46) is decided — the repository has been transferred to the cncf GitHub org — so the announcement can point at the site's permanent home; DNS cutover itself remains the Phase 3 follow-up (see Non-goals).

Non-goals

  • DNS cutover to endusers.cncf.io itself (Phase 3; follows the ownership decision — nice to have for launch, not required to announce).
  • Paid promotion, swag, or a booth presence.

Timeline (weeks are Mondays)

Week Date Milestone
W-13 2026-08-11 Merge LICENSE (#40) and close Phase 0; create the four GitHub milestones (#78) so every launch task is tagged
W-12 2026-08-17 ADR 0001 ownership decision made (#46/#99) — this gates the announcement target and DNS work
W-11 2026-08-24 Metrics refresh workflow landed (#74); events page lists KubeCon NA 2026 co-located end-user events (#75)
W-10 2026-08-31 Awards list verified complete against cncf.io announcements (#77)
W-9 2026-09-07 Architectures freshness indicator on-page (#80); community/TAB staleness signal (#79)
W-8 2026-09-14 Good-first-issue curation done (#98); CONTRIBUTING walk-through by someone who didn't write it
W-7 2026-09-21 Blog cadence resumes: first post-welcome article (#76) — end-user story or architecture deep-dive
W-6 2026-09-28 Success-metrics baseline captured (see below) and dashboard/tracking issue live (#100)
W-5 2026-10-05 Launch blog post drafted; announcement channels confirmed (CNCF blog/Twitter amplification, end-user Slack, TAB mailing list)
W-4 2026-10-12 Full content freeze rehearsal: every generated-data workflow runs green end-to-end
W-3 2026-10-19 Launch blog post reviewed; DNS cutover executed if ownership decision landed on a CNCF org (Phase 3)
W-2 2026-10-26 Dry-run announcement to end-user community Slack; collect last-mile fixes
W-1 2026-11-02 Final content refresh; all Phase 1 issues closed or explicitly deferred
W-0 2026-11-09 Launch during KubeCon NA week: publish launch post, amplify on agreed channels, open feedback issue template

Success metrics (baseline + post-launch targets)

Five of the signals below are machine-collected in data/launch-metrics.json (issue #100) rather than hand-tracked here, so they can't go stale the way a one-time table does: refresh with npm run collect:launch-metrics, validate with npm run validate:launch-metrics. Re-run the collector at (or after) the W-6 checkpoint (2026-09-28) so the committed baseline reflects that checkpoint — see the file's own checkpoint field for the current status. The two signals without a GitHub API source (blog cadence, cncf.io referral) are tracked here as prose and checked manually.

Signal Baseline 90-day post-launch target Source
GitHub stars see data/launch-metrics.json 50 data/launch-metrics.json
GitHub watchers see data/launch-metrics.json 10 data/launch-metrics.json
GitHub forks see data/launch-metrics.json 5 data/launch-metrics.json
New unique human contributors since baseline 0 (by definition) 5 data/launch-metrics.json
Good-first-issues claimed see data/launch-metrics.json 3 data/launch-metrics.json
Blog posts since launch 0 2 (launch post + 1 community voice) manual (blog/)
Referral from cncf.io properties none cross-link merged on at least one CNCF property (Phase 3) manual

Launch-readiness gate: zero-red content pipelines (#136)

The site's differentiator over static CNCF documentation is living, self-refreshing community data. Launching with red scheduled pipelines means shipping stale content on day one — the exact failure this automation exists to prevent. Before the W-0 launch date, all scheduled content-refresh workflows must be green for 2 consecutive scheduled runs. The default-branch deployment is listed as a separate operational prerequisite. Statuses below were verified against main workflow runs on 2026-10-01 UTC:

Pipeline Schedule Status verified 2026-10-01 UTC Tracking
Default-branch deployment (deploy-gh-pages.yml) Every push to main Green: 2026-09-30 00:58:40 UTC and 2026-10-01 02:45:00 UTC; both build and deploy jobs succeeded Operational prerequisite
Import reference architectures (import-architectures.yml) On-demand (workflow_dispatch) Last successful run: 2026-09-28 02:46:46 UTC; no post-migration workflow_dispatch run is recorded #121 (closed; reopen a new issue if this regresses)
Refresh community profiles (refresh-community-people.yml) Weekly Green (1 of 2 consecutive scheduled runs: 2026-09-28 02:55:29 UTC; the next scheduled run has not yet occurred) #568 (closed; reopen a new issue if this regresses)
Metrics refresh (collect:metrics + validate:metrics steps of import-architectures.yml) On-demand (workflow_dispatch) collect:metrics, validate:metrics, and import steps succeeded in the 2026-09-28 02:46:46 UTC run; no post-migration workflow_dispatch run is recorded #121 (closed; reopen a new issue if this regresses)
Refresh radar reports (refresh-radar-reports.yml) Daily Green on 2026-09-28 03:04:01 UTC, 2026-09-29 03:00:48 UTC, and 2026-09-30 03:01:56 UTC #605 (closed; reopen a new issue if this regresses)

import-architectures.yml moved from a daily cron to on-demand only (workflow_dispatch); a maintainer or contributor now triggers an import run manually instead of it recurring unattended. Its "2 consecutive scheduled runs" gate history above predates that change and is retained for context; the pipeline is no longer subject to the scheduled-run gate this section otherwise requires, since it has no schedule to run on.

A dedicated refresh-metrics.yml workflow was proposed in PR #125 and declined (#74); metrics refresh instead runs as steps inside import-architectures.yml, so it shares that workflow's tracking issue and readiness signal.

Issue #121 and its predecessor for the refresh-community-people GITHUB_TOKEN permission error (#122, duplicate of #519) are closed, but closing a tracking issue does not by itself mean the pipeline is green: the status column above must be checked against the workflow's actual run history (gh run list --workflow <name>) before treating a row as resolved. The 2026-09-28 community-profile run and the architecture/metrics run both report contents: write and pull-requests: write in their effective GITHUB_TOKEN permissions and complete their create-pull-request steps. Issue #568 (missing signoff: true on create-pull-request steps) was closed and the 2026-09-28 scheduled run succeeded; one more consecutive green scheduled run is required to satisfy the gate before W-0.

If any pipeline is still red at W-1, treat it the same as any other Phase 1 blocker under "Full content freeze rehearsal" (W-4): either land the fix or explicitly defer the affected content pillar in the launch post rather than presenting it as current.

Dependencies and risks

  • Ownership decision (ADR 0001) is resolved — Accepted, and the repository has been transferred to the cncf GitHub org. What remains on the critical path is executing the DNS cutover to endusers.cncf.io itself (Phase 3, issue #46), not the decision.
  • Merge throughput (#58): the plan assumes the human merge gate keeps its current burst cadence; the W-13 and W-12 items are all merge-gated, not work-gated.
  • Content freshness workflows (#74, #75, #79, #80) have landed — remaining risk is regression before launch, not initial rollout.

How to use this file

Track execution against the table above in the matching issues; when a week slips, update the table in a PR labeled roadmap rather than letting the plan drift. After KubeCon, replace this file with a launch retrospective.